5. Cost Estimation
5.1 Costs Associated with Constructed Facilities
The costs of a constructed facility to the owner include both the initial capital cost and the subsequent operation and maintenance costs. Each of these major cost categories consists of a number of cost components.
The capital cost for a construction project includes the expenses related to the inital establishment of the facility:
Land acquisition, including assembly, holding and improvement
Planning and feasibility studies
Architectural and engineering design
Construction, including materials, equipment and labor
Field supervision of construction
Construction financing
Insurance and taxes during construction
Owner"s general office overhead
Equipment and furnishings not included in construction
Inspection and testing
The operation and maintenance cost in subsequent years over the project life cycle includes the following expenses:
Land rent, if applicable
Operating staff
Labor and material for maintenance and repairs
Periodic renovations
Insurance and taxes
Financing costs
Utilities
Owner"s other expenses
输入限制,不能636fa686964616f全部发给你,参考以下网址
或交流,还有很多,不能全部收录。
Project Management and Cost
Jim Sloman
Chief Executive and Director
MI Associates
Former Chief Operating Officer
Sydney Organising Committee for the Olympic Games
Australia
这篇的长度合适PDF8页
相关热词 : 工程造价论文